Excellent progress being made on our new build substation project in North Yorkshire.
The structures team are hard at it aiming to have all RC works complete by the end of November and the Civils team aiming to have the last of the deep excavations complete with the Cess pit installation.
This project was also fortunate to take delivery of a new 8t CAT Excavator supplied by our sister company O’Rourke Plant.
Massive thank you to the site team and backroom staff who are working tirelessly to get the bulk of the works complete this side of Christmas.
Also thank you to our supply chain who are supporting us effortlessly.