O’Rourke Construction Ltd (OCL) were contracted by our repeat client to undertake the following works from the AIS to the GIS within New Cumnock substation.
- Supply of all site documentation preconstruction
- Supply of all site management, engineers, supervisors, Health & Safety
- All Excavation works
- Supply and installation of concrete ODSE foundations for 2no. circuits
- Supply and installation of ODSE structures for 2no. circuits
- All Temporary works designs
- Duct installation for 2no. circuits
- All reinstatement works
- Installation of 132kv cable
- Installation of Fibre Optic cable
- Supply of scaffolding around the AIS structures and the GIS structures
- Supply of all plant, equipment and materials for the project